RDF pretreatment

Through the practice of more than 30 engineering projects in China and abroad, the Sequoia team has accumulated a complete alternative fuel pretreatment scheme and developed distinctive products for the pretreatment process.
The process system integration we can provide includes:
  • Plastic Preparation Process (PPP)
  • Tire Preparation Process (TPP)
  • Domestic Waste Preparation (MTP, Mechanical-Thermal Process)
  • Wood Preparation Process (WPP)
  • Animal Meal Preparation Process (APP)
  • Waste Oil Preparation Process (OPP)
  • Sewage Sludge Preparation Process (SPP)
  • Wood / Husk Rice / Biomass Drying Process with waste heat/solar
  • Any other type of secondary fuels
The main products include: alternative fuel pretreatment dust removal equipment,  drying equipment,rdf bins etc.
If you have detailed engineering projects in need, please contact us in a timely manner.(Contact us)。

Frequently Asked Technical Questions

Q1. What does a typical RDF pretreatment line look like, from raw municipal waste to cement-knee-ready fuel?
A modern RDF (refuse-derived fuel) line follows four stages. First, bag-breaking and trommel screening at a 80-120 mm aperture separates fines (organics, glass) from the oversize combustible fraction. Second, pre-shredding with a single-shaft shear shredder (Vecoplan VEZ, UNTHA XR series) reduces raw waste to 200-300 mm. Third, sorting: magnetic and eddy-current separators remove ferrous and non-ferrous metals; a ballistic separator (e.g. Ballistor width 2,400-4,960 mm) splits 2D film/paper from 3D rigid plastics; NIR optical sorters (Cimbria SEA) eject PVC and PET to control chlorine. Fourth, fine shredding to a nominal top size of 30 mm (d95 per CEN/TS 15415) and optional pelletizing/briquetting to raise bulk density from 0.15 to 0.5-0.7 t/m3. Vecoplan’s Irish Cement reference feeds 840 t/d of RDF to the preheater tower and main burner, demonstrating the scale at which such lines run.

Q2. What particle size, heating value and chlorine limits must cement-grade RDF meet?
Cement plants generally require RDF (or SRF, solid recovered fuel) classified per EN 15359:2011. For calciner firing, a typical spec is: nominal top size 30 mm (d95), moisture below 25% as-received, lower heating value (LHV) at least 15 MJ/kg as-received (high-quality SRF targets 20 MJ/kg dry), chlorine below 0.5-1.0% dry basis, and ash below 20%. A Polish EU tender published on EUR-Lex specifies exactly this: shredded to 30 mm, LHV above 17,000 kJ/kg, chlorine up to 0.7%, moisture up to 25%. BMH’s Cimpor Alhandra reference feeds 2 x 5 t/h of 30×30 mm RDF to the kiln main burner. Firing RDF above these limits raises chlorine circulation, causes KCl/NaCl condensation in preheater cyclones at 700 degC, and increases dioxin and HCl risk in the cooler gas.

Q3. How much electrical energy does RDF shredding consume, and how is the line sized?
Shredding is the most energy-intensive unit in pretreatment. Single-shaft shredders such as the UNTHA XR3000C process up to 15 t/h of mixed waste at operating costs below EUR 5/t and specific energy consumption of roughly 15-35 kWh/t for a two-stage process (pre-shred to 300 mm, then fine shred to 30 mm). The UNTHA RDF line reaches up to 70 t/h throughput; its C-cutter geometry gives a constant material feed and a homogeneous output, demonstrated at 20 t/h for paper-mill rejects. Vecoplan’s VEZ series uses a direct-drive HiTorc motor that delivers high torque at low speed without a gearbox, cutting both energy use and maintenance. Overall, a 100 t/d RDF line draws 300-500 kW installed, and the shredder typically accounts for 40-50% of plant electricity. Sizing is driven by the kiln’s daily RDF demand divided by 16-20 operating hours, with 30% spare capacity for wear screen changes.

Q4. How are chlorine, PVC and alkali metals controlled to protect the cement kiln?
Chlorine from PVC and food waste is the limiting element for high substitution. In the kiln, chlorine evaporates in the burning zone (~1,450 degC), migrates to the preheater, condenses as alkali chlorides (KCl, NaCl) at 700-900 degC on raw meal particles, and recycles, causing rings and blockages. Holtec’s guidance keeps chlorine below 0.015% in kiln feed and uses a 5% chlorine bypass to bleed off the circulating gas, recovering KCl-rich dust. On the pretreatment side, NIR optical sorters (Cimbria) eject PVC at up to 99.99% plastic-stream purity, and ballistic separation removes film which carries much of the chlorine-rich packaging waste. The alkali/(SO3+2Cl) molar balance should be held near 1.0 so that alkalis preferentially bind sulfate rather than chloride. Dioxin control is achieved by ensuring kiln gas residence time above 850 degC for at least 2 seconds, which the 1,000-second prepol SC combustor comfortably exceeds.

author avatar
Jacob CEO
An expert in pyroprocess and solidwaste recovery . Responsible for the Marketing and Support of Sequoia Industrial with over 14 years in this field. I am determined that our sustainable products and services will be at the forefront of the solution for the generations to come.
未经允许不得转载:Nanjing Sequoia Industrial Solutions Co.,ltd » RDF pretreatment
Share to
1 Likes
Next page

相关推荐

Comments (0)

联系我们

(86)17701582266

CopyCopied

+8617701582266

CopyCopied
WeChat
(86)17701582266CopyCopied
Follow our official WeChat,get the latest information
contact-img
Whatsapp
+8617701582266CopyCopied
Official account
contact-img